How Power Connects to Your Container
Every batch of office containers is built a little differently, so the exact spot where power connects depends on your unit. Your container will match one of the three setups below. The requirement is the same for all of them, 120/240V single phase, and any hard-wiring into a breaker panel should be done by a qualified electrician. Not sure which setup you have? Send us a photo and we will tell you.
Setup 1
Exterior Breaker Panel
The breaker box mounted on the outside of the container, circled in red.
Many containers have the breaker box mounted on the outside. An electrician wires land power or generator power straight into it from outside, so no cable pass-through is needed.
Setup 2
Interior Breaker Panel
An interior breaker box (circled red) with the exterior cable pass-through (circled green) used to route the wires inside.
Some containers have the breaker box inside. An electrician feeds the wires through the exterior cable pass-through, a small port low on the container wall, then runs them up to the panel inside. It takes an extra step, but it powers the container the same way.
Setup 3
Direct Generator Hookup
A 50-amp generator inlet built into the exterior wall. Some containers have this, but not many.
A few units have a 50-amp inlet built right into the outside wall. If yours does, a properly sized generator connects with a compatible cord and no hard-wiring, which makes it the quickest generator setup. Land power still wires into the breaker panel.